High severity — Estimated arrival 2026-08-20 is later than required delivery date 2026-08-14.
Situation, decision support, evidence and workflow state for one operational exception.
Estimated arrival 2026-08-20 is later than required delivery date 2026-08-14.
| Exception | EXC-001473 · High | Shipment status | Delayed |
|---|---|---|---|
| Route | Shenzhen → Paris | Mode / Carrier | Rail · CAR-005 |
| Route detail | Shenzhen → Paris | Planned departure | 2026-08-04 |
| Estimated arrival | 2026-08-20 | Required delivery | 2026-08-14 |
| Order / Customer | ORD-04767 · Nordic Electronics GmbH | Exception status | Open |
Based on the separation between this option's score (83.77) and the next-best alternative's score (81.74) - a gap of 2.03 points.
| Alternative | Cost | Transit (days) | Risk | Decision score | Confidence |
|---|---|---|---|---|---|
| OPT-003358 — Air | 4251.52 | 2 | 44 | 81.74 | — |
| Factor | Weight | OPT-003359 (Road) | OPT-003358 (Air) |
|---|---|---|---|
| Cost fit | 0.25 | 73.97 (18.49) | 49.97 (12.49) |
| Transit fit | 0.3 | 93.75 (28.12) | 100 (30) |
| Risk fit | 0.25 | 68.6 (17.15) | 81 (20.25) |
| Priority fit | 0.2 | 100 (20) | 95 (19) |
Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.
Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (2.03 points). It is not a probability of success.
Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-08-20 is later than required delivery date 2026-08-14.
Recovery options evaluated — Adensa recovery engine
3 options assessed; 2 feasible — 1 infeasible
Recommendation generated — Adensa decision engine
ACT-000801 — Recommended recovery: switch shipment to Road using carrier CAR-001. Estimated cost: €3,051.53. Estimated transit: 4.0 days. Risk score: 54.0.
Exception still open — Adensa operational pipeline
Current status: Open — estimated arrival 2026-08-20 still misses required delivery 2026-08-14 — monitored until recovery is recorded
Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.
| Option | Mode | Estimated CO₂e (kg) | vs Recommended |
|---|---|---|---|
| OPT-003359 | Road | 347.41 | — |
| OPT-003358 | Air | 2084.45 | Higher |
Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.
Current state: Decision required
Recovery action ACT-000801 is awaiting a planner approval or rejection decision.