Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-07-18 is later than required delivery date 2026-07-06.
Situation, decision support, evidence and workflow state for one operational exception.
Estimated arrival 2026-07-18 is later than required delivery date 2026-07-06.
| Exception | EXC-001442 · High | Shipment status | Delivered |
|---|---|---|---|
| Route | Tokyo → Hamburg | Mode / Carrier | Sea · CAR-003 |
| Route detail | Tokyo → Hamburg | Planned departure | 2026-06-21 |
| Estimated arrival | 2026-07-18 | Required delivery | 2026-07-06 |
| Order / Customer | ORD-04667 · EuroTech Distribution AG | Exception status | Open |
Based on the separation between this option's score (85.34) and the next-best alternative's score (83.58) - a gap of 1.76 points.
| Alternative | Cost | Transit (days) | Risk | Decision score | Confidence |
|---|---|---|---|---|---|
| OPT-003292 — Air | 3883.55 | 2 | 44 | 83.58 | — |
| OPT-003294 — Rail | 2583.55 | 10 | 59 | 68.99 | — |
| Factor | Weight | OPT-003293 (Road) | OPT-003292 (Air) | OPT-003294 (Rail) |
|---|---|---|---|---|
| Cost fit | 0.25 | 80.27 (20.07) | 57.33 (14.33) | 81.94 (20.49) |
| Transit fit | 0.3 | 93.75 (28.12) | 100 (30) | 57.86 (17.36) |
| Risk fit | 0.25 | 68.6 (17.15) | 81 (20.25) | 60.6 (15.15) |
| Priority fit | 0.2 | 100 (20) | 95 (19) | 80 (16) |
Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.
Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (1.76 points). It is not a probability of success.
Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-07-18 is later than required delivery date 2026-07-06.
Recovery options evaluated — Adensa recovery engine
3 options assessed; 3 feasible — 0 infeasible
Recommendation generated — Adensa decision engine
ACT-000785 — Recommended recovery: switch shipment to Road using carrier CAR-001. Estimated cost: €2,683.55. Estimated transit: 4.0 days. Risk score: 54.0.
Exception still open — Adensa operational pipeline
Current status: Open — estimated arrival 2026-07-18 still misses required delivery 2026-07-06 — monitored until recovery is recorded
Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.
| Option | Mode | Estimated CO₂e (kg) | vs Recommended |
|---|---|---|---|
| OPT-003293 | Road | 15.25 | — |
| OPT-003292 | Air | 91.51 | Higher |
| OPT-003294 | Rail | 4.27 | Lower |
Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.
Current state: Decision required
Recovery action ACT-000785 is awaiting a planner approval or rejection decision.