Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-09-14 is later than required delivery date 2026-09-01.
Situation, decision support, evidence and workflow state for one operational exception.
Estimated arrival 2026-09-14 is later than required delivery date 2026-09-01.
| Exception | EXC-001416 · High | Shipment status | Delivered |
|---|---|---|---|
| Route | Shanghai → Frankfurt | Mode / Carrier | Sea · CAR-003 |
| Route detail | Shanghai → Frankfurt | Planned departure | 2026-08-19 |
| Estimated arrival | 2026-09-14 | Required delivery | 2026-09-01 |
| Order / Customer | ORD-04585 · Nordic Electronics GmbH | Exception status | Open |
Based on the separation between this option's score (84.22) and the next-best alternative's score (82.24) - a gap of 1.98 points.
| Alternative | Cost | Transit (days) | Risk | Decision score | Confidence |
|---|---|---|---|---|---|
| OPT-003232 — Air | 4152.85 | 2 | 44 | 82.24 | — |
| OPT-003234 — Rail | 2852.85 | 10 | 59 | 67.87 | — |
| Factor | Weight | OPT-003233 (Road) | OPT-003232 (Air) | OPT-003234 (Rail) |
|---|---|---|---|---|
| Cost fit | 0.25 | 75.79 (18.95) | 51.94 (12.99) | 77.45 (19.36) |
| Transit fit | 0.3 | 93.75 (28.12) | 100 (30) | 57.86 (17.36) |
| Risk fit | 0.25 | 68.6 (17.15) | 81 (20.25) | 60.6 (15.15) |
| Priority fit | 0.2 | 100 (20) | 95 (19) | 80 (16) |
Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.
Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (1.98 points). It is not a probability of success.
Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-09-14 is later than required delivery date 2026-09-01.
Recovery options evaluated — Adensa recovery engine
3 options assessed; 3 feasible — 0 infeasible
Recommendation generated — Adensa decision engine
ACT-000770 — Recommended recovery: switch shipment to Road using carrier CAR-001. Estimated cost: €2,952.85. Estimated transit: 4.0 days. Risk score: 54.0.
Exception still open — Adensa operational pipeline
Current status: Open — estimated arrival 2026-09-14 still misses required delivery 2026-09-01 — monitored until recovery is recorded
Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.
| Option | Mode | Estimated CO₂e (kg) | vs Recommended |
|---|---|---|---|
| OPT-003233 | Road | 78.94 | — |
| OPT-003232 | Air | 473.65 | Higher |
| OPT-003234 | Rail | 22.1 | Lower |
Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.
Current state: Decision required