EXC-001398 — Delivery Delay

Shipment SHP-04533 · Order ORD-04533 · Paris Connected Systems

CriticalDecision required
  1. DetectedCompleted
  2. DecisionCurrent
  3. ExecutionUpcoming
  4. OutcomeUpcoming

Situation & Impact

Estimated arrival 2026-04-20 is later than required delivery date 2026-04-13.

ExceptionEXC-001398 · CriticalShipment statusDelivered
RouteSeoul → ParisMode / CarrierRail · CAR-003
Route detailSeoul → ParisPlanned departure2026-03-31
Estimated arrival2026-04-20Required delivery2026-04-13
Order / CustomerORD-04533 · Paris Connected SystemsException statusOpen

Decision Support

AlternativeCostTransit (days)RiskDecision scoreConfidence
OPT-003194 — Road2930.9546478.31—
Why this recommendation
FactorWeightOPT-003193 (Air)OPT-003194 (Road)
Cost fit0.2552.38 (13.1)76.15 (19.04)
Transit fit0.3100 (30)93.75 (28.12)
Risk fit0.2568.6 (17.15)52.6 (13.15)
Priority fit0.2100 (20)90 (18)

Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.

  • OPT-003194 (Road) is stronger on Cost fit.

Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (1.94 points). It is not a probability of success.

Operational History

  1. 2026-09-10 12:00:00

    Exception detected — Adensa operational pipeline

    Critical severity — Estimated arrival 2026-04-20 is later than required delivery date 2026-04-13.

  2. —

    Recovery options evaluated — Adensa recovery engine

    3 options assessed; 2 feasible — 1 infeasible

  3. —

    Recommendation generated — Adensa decision engine

    ACT-000761 — Recommended recovery: switch shipment to Air using carrier CAR-001. Estimated cost: €4,130.95. Estimated transit: 2.0 days. Risk score: 54.0.

  4. —

    Exception still open — Adensa operational pipeline

    Current status: Open — estimated arrival 2026-04-20 still misses required delivery 2026-04-13 — monitored until recovery is recorded

Sustainability Impact

Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.

Emissions estimates (2 options) & methodology
OptionModeEstimated CO₂e (kg)vs Recommended
OPT-003193Air389.81—
OPT-003194Road64.97Lower

Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.

Workflow Action

Current state: Decision required

Recovery action ACT-000761 is awaiting a planner approval or rejection decision.

Review the recommendation and record the approval or rejection decision.