EXC-001196 — Delivery Delay

Shipment SHP-03899 · Order ORD-03899 · Alpine Digital Solutions

MediumExecuted — still open
  1. DetectedCompleted
  2. Manual resolutionCurrent
  3. OutcomeUpcoming

Situation & Impact

Estimated arrival 2026-06-12 is later than required delivery date 2026-06-09.

ExceptionEXC-001196 · MediumShipment statusIn Transit
RouteTokyo → HamburgMode / CarrierAir · CAR-001
Route detailTokyo → HamburgPlanned departure2026-06-07
Estimated arrival2026-06-10Required delivery2026-06-09
Order / CustomerORD-03899 · Alpine Digital SolutionsException statusOpen

Decision Support

No comparable alternatives were evaluated.

Why this recommendation
FactorWeightOPT-002740 (Air)
Cost fit0.2581.2 (20.3)
Transit fit0.3100 (30)
Risk fit0.2581 (20.25)
Priority fit0.280 (16)

Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.

Confidence basis: High confidence reflects a single feasible recovery option, not a probability of success.

Operational History

  1. 2026-06-07 08:00:00

    Exception detected — Adensa operational pipeline

    Medium severity — Estimated arrival 2026-06-12 is later than required delivery date 2026-06-09.

  2. —

    Recovery options evaluated — Adensa recovery engine

    3 options assessed; 1 feasible — 2 infeasible

  3. 2026-06-07 12:00:00

    Recommendation generated — Adensa decision engine

    ACT-000662 — Recommended recovery: switch shipment to Air using carrier CAR-001. Estimated cost: €2,628.20. Estimated transit: 2.0 days. Risk score: 44.0.

  4. 2026-06-07 12:00:00

    Recovery approved — M. Okafor

    ACT-000662 by M. Okafor

  5. 2026-06-08 00:00:00

    Recovery executed — M. Okafor

    ACT-000662 — shipment recovered through the system recovery workflow

  6. —

    Exception still open — Adensa operational pipeline

    Current status: Open — estimated arrival 2026-06-10 still misses required delivery 2026-06-09 — monitored until recovery is recorded

Sustainability Impact

Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.

Emissions estimates (1 option) & methodology
OptionModeEstimated CO₂e (kg)vs Recommended
OPT-002740Air445.21—

Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.

Workflow Action

Current state: Executed — still open

Recovery executed, but estimated arrival 2026-06-10 remains later than required delivery 2026-06-09. Exception remains open after recovery execution.

The recovery action was executed; the exception remains open and requires follow-up.