Exception detected — Adensa operational pipeline
Medium severity — Estimated arrival 2026-09-02 is later than required delivery date 2026-08-30.
Situation, decision support, evidence and workflow state for one operational exception.
Estimated arrival 2026-09-02 is later than required delivery date 2026-08-30.
| Exception | EXC-000927 · Medium | Shipment status | In Transit |
|---|---|---|---|
| Route | Shanghai → Rotterdam | Mode / Carrier | Rail · CAR-003 |
| Route detail | Shanghai → Rotterdam | Planned departure | 2026-08-19 |
| Estimated arrival | 2026-09-02 | Required delivery | 2026-08-30 |
| Order / Customer | ORD-03063 · Central Europe Components | Exception status | Open |
Based on the separation between this option's score (90.28) and the next-best alternative's score (90.19) - a gap of 0.09 points.
| Alternative | Cost | Transit (days) | Risk | Decision score | Confidence |
|---|---|---|---|---|---|
| OPT-002128 — Air | 2473.88 | 2 | 44 | 90.19 | — |
| Factor | Weight | OPT-002129 (Road) | OPT-002128 (Air) |
|---|---|---|---|
| Cost fit | 0.25 | 100 (25) | 83.77 (20.94) |
| Transit fit | 0.3 | 93.75 (28.12) | 100 (30) |
| Risk fit | 0.25 | 68.6 (17.15) | 81 (20.25) |
| Priority fit | 0.2 | 100 (20) | 95 (19) |
Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.
Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (0.09 points). It is not a probability of success.
Exception detected — Adensa operational pipeline
Medium severity — Estimated arrival 2026-09-02 is later than required delivery date 2026-08-30.
Recovery options evaluated — Adensa recovery engine
3 options assessed; 2 feasible — 1 infeasible
Recommendation generated — Adensa decision engine
ACT-000514 — Recommended recovery: switch shipment to Road using carrier CAR-001. Estimated cost: €1,273.88. Estimated transit: 4.0 days. Risk score: 54.0.
Exception still open — Adensa operational pipeline
Current status: Open — estimated arrival 2026-09-02 still misses required delivery 2026-08-30 — monitored until recovery is recorded
Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.
| Option | Mode | Estimated CO₂e (kg) | vs Recommended |
|---|---|---|---|
| OPT-002129 | Road | 9.29 | — |
| OPT-002128 | Air | 55.74 | Higher |
Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.
Current state: Decision required
Recovery action ACT-000514 is awaiting a planner approval or rejection decision.