Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-09-16 is later than required delivery date 2026-09-09.
Situation, decision support, evidence and workflow state for one operational exception.
Estimated arrival 2026-09-16 is later than required delivery date 2026-09-09.
| Exception | EXC-000543 · High | Shipment status | Delayed |
|---|---|---|---|
| Route | Tokyo → Hamburg | Mode / Carrier | Rail · CAR-002 |
| Route detail | Tokyo → Hamburg | Planned departure | 2026-08-24 |
| Estimated arrival | 2026-09-16 | Required delivery | 2026-09-09 |
| Order / Customer | ORD-01841 · EuroTech Distribution AG | Exception status | Open |
Based on the separation between this option's score (86.88) and the next-best alternative's score (82.43) - a gap of 4.45 points.
| Alternative | Cost | Transit (days) | Risk | Decision score | Confidence |
|---|---|---|---|---|---|
| OPT-001219 — Air | 3514.8 | 2 | 44 | 82.43 | — |
| Factor | Weight | OPT-001220 (Road) | OPT-001219 (Air) |
|---|---|---|---|
| Cost fit | 0.25 | 86.42 (21.61) | 64.7 (16.18) |
| Transit fit | 0.3 | 93.75 (28.12) | 100 (30) |
| Risk fit | 0.25 | 68.6 (17.15) | 81 (20.25) |
| Priority fit | 0.2 | 100 (20) | 80 (16) |
Each cell: factor score (weighted contribution to the decision score). Weights are policy configuration — unchanged by this view.
Confidence basis: Derived from the separation between the recommended option's score and the next-best alternative (4.45 points). It is not a probability of success.
Exception detected — Adensa operational pipeline
High severity — Estimated arrival 2026-09-16 is later than required delivery date 2026-09-09.
Recovery options evaluated — Adensa recovery engine
3 options assessed; 2 feasible — 1 infeasible
Recommendation generated — Adensa decision engine
ACT-000309 — Recommended recovery: switch shipment to Road using carrier CAR-001. Estimated cost: €2,314.80. Estimated transit: 4.0 days. Risk score: 54.0.
Exception still open — Adensa operational pipeline
Current status: Open — estimated arrival 2026-09-16 still misses required delivery 2026-09-09 — monitored until recovery is recorded
Informational only — estimated emissions (kg CO₂e) never affect the recovery recommendation. Prototype sustainability estimate based on persisted shipment data and configured factors; distance is the persisted route distance, not live routing data.
| Option | Mode | Estimated CO₂e (kg) | vs Recommended |
|---|---|---|---|
| OPT-001220 | Road | 62.78 | — |
| OPT-001219 | Air | 376.65 | Higher |
Methodology: Estimated transport emissions = shipment tonnes × route kilometres × configured mode factor. Factors are prototype assumptions, not measured data.
Current state: Decision required
Recovery action ACT-000309 is awaiting a planner approval or rejection decision.